Southwest LRT begins on‑track testing

Metro Transit started moving test trains on the Green Line Extension/Southwest LRT on Tuesday, Oct. 14, towing up to six light-rail vehicles from Target Field Station to SouthWest Station in Eden Prairie at no more than 5 mph with clearance 'feeler' extensions. The 14.5‑mile line, about 85% complete, will see daily train movements during months of testing and operator training ahead of projected 2027 passenger service, with a public safety campaign urging people to use only designated crossings.

Transit & Infrastructure Public Safety

📌 Key Facts

  • Initial tests tow up to six LRVs at ≤5 mph from Minneapolis to Eden Prairie starting Oct. 14, 2025
  • Trains will be present on the corridor daily during months of testing and training; service targeted for 2027
  • Project spans 14.5 miles through Minneapolis, St. Louis Park, Hopkins, and Minnetonka; budget rose to $2.86B as of Jan. 2024